Port Everglades Turning Notch Review

Bermello Ajamil & Partners enlisted Orion for a peer review of Port Everglades Turning Notch project in Fort Lauderdale. Our team assessed design, schedule, cost estimate, and excavation alternatives, delivering valuable recommendations. The project involved constructing new bulkheads, toe walls, environmentally friendly bulkheads, extensive upland excavation and dredging, and a paved container yard.

PROJECT HIGHLIGHTS

  • Construction of 3,183lf of new deep-water bulkhead and fenders
  • Construction of 990lf of toe wall
  • Construction of 1,600lf of Environmentally Friendly Bulkhead
  • Upland excavation and dredging of 26 acres
  • Construction of 24 acres of paved upland container yard

Comprehensive Peer Review

Orion was engaged by Bermello Ajamil & Partners to do a comprehensive peer review of the Port Everglades Turning Notch project in Fort Lauderdale, Florida. The scope encompassed evaluating the design concept, project schedule, construction cost estimate, and excavation alternatives. The project itself entailed substantial construction elements, including the installation of 3,183lf of new deep-water bulkhead and fenders, 990lf of toe wall, and 1,600lf of an Environmentally Friendly Bulkhead. Additionally, it involved upland excavation and dredging spanning 26 acres, along with the construction of a 24-acre paved upland container yard.

Our team analyzed each aspect of the project, providing a detailed written narrative of review findings. The review extended to recommendations aimed at enhancing the overall value and efficiency of the Port Everglades Turning Notch endeavor. By scrutinizing the design, schedule, cost estimate, and excavation alternatives, we contributed valuable insights to optimize the project's success. The thorough examination facilitated a comprehensive understanding of the project's intricacies and potential improvements, highlighting Orion’s commitment to delivering impactful results.